The Strata Management Tribunal (Tribunal Pengurusan Strata, TPS) is KPKT’s low-cost forum for strata disputes under the Strata Management Act 2013. It hears claims of up to RM250,000, such as unpaid maintenance charges and sinking fund, inter-floor leaks, meeting resolutions and by-law disputes. You file Form 1 (Statement of Claim) with a filing fee reported at RM100, lawyers are generally not allowed, and the tribunal aims to make its award within 60 days of the first hearing where practicable. Its southern zone office is in Johor Bahru.
Most strata issues are settled with a conversation or at the AGM. But sometimes a neighbour’s leak will not get fixed, an owner will not pay, or a resolution looks wrong. Do you need to hire a lawyer and go to court? Usually not. Malaysia has a dedicated tribunal for exactly these disputes, and it is designed to be quick, cheap and usable without legal representation.
This page answers the questions JB owners and buyers ask most about the Strata Management Tribunal, checked against KPKT’s own tribunal pages and published guidance.
What is the Strata Management Tribunal?
It is a tribunal set up under the Strata Management Act 2013 (Act 757) to resolve strata disputes faster and more cheaply than the civil courts. It sits within KPKT’s Housing and Strata Management Tribunal (Tribunal Perumahan dan Pengurusan Strata, TPPS), alongside the Tribunal for Homebuyer Claims.
It is busy and well established. KPKT reported in July 2025 that the TPPS registered 12,883 cases in 2024 and resolved 11,839, and that strata tribunal awards in 2024 were worth about RM60.05 million. At that time there were 28 TPS presidents hearing strata cases.
What disputes does the tribunal handle?
The tribunal hears the disputes listed in Part 1 of the Fourth Schedule of the Act. The main categories include:
- Recovery of unpaid maintenance charges and sinking fund contributions
- Monetary claims of up to RM250,000
- Defect repair costs, including inter-floor leaks between units
- Orders to convene a general meeting, invalidate meeting proceedings or nullify a resolution
- Revoking by-law amendments, varying late-payment interest or insurance amounts
- Disclosure of information or documents by the management body
- Consent for alterations to common property
- Affirming, varying or revoking a decision of the Commissioner of Buildings
Money is the biggest theme. The tribunal’s deputy chairman said in 2022 that about 80% of claims relate to collecting or paying fees, about 10% to meetings and about 10% to management operations.
What is the claim limit?
RM250,000. Claims above this need to be taken to the courts instead. For most strata disputes, such as arrears, leak repairs or a disputed resolution, the amount involved is well within the limit.
How much is the filing fee?
The filing fee is RM100, according to the tribunal’s deputy chairman speaking in 2022. That is a fraction of the cost of a court action. KPKT’s tribunal pages list the forms but not the fee, so confirm the current amount with the tribunal when you file.
Who can file a claim?
Eight types of parties can bring or answer a claim: parcel owners, purchasers, developers, joint management bodies, management corporations, subsidiary management corporations, managing agents and other stakeholders recognised under the Act. In practice, owners usually file about leaks, records or meeting decisions, and management bodies usually file to recover unpaid charges.
How does the process work?
- File Form 1 (Statement of Claim) with the tribunal and pay the filing fee. KPKT has been rolling out e-TPS to let claims be filed digitally rather than at a counter.
- Serve the claim on the other party. The respondent can reply with Form 2 (Statement of Defence and Counterclaim), and the claimant can answer a counterclaim with Form 3.
- Attend the hearing. A Notice of Hearing (Form 4) sets the date. Parties present their own case with documents, photos and quotations.
- Receive the award. It is issued as an Award after Hearing (Form 11) or an Award by Consent (Form 6) if the parties settle.
- Comply or enforce. The award is treated as an order of the civil court and can be enforced.
How long does it take?
The Act requires the tribunal to make its award without delay and, where practicable, within 60 days of the first hearing day. KPKT’s client charter for the strata tribunal targets resolving claims within 140 working days of filing and serving awards within 10 working days of the award date.
Do I need a lawyer?
Generally no. Parties are not normally represented by lawyers. The tribunal can allow it where a case raises complex legal issues and a party would otherwise suffer severe financial hardship, and if one side is allowed a lawyer, the other must be too. You can still take legal advice while preparing your papers.
What if the other side ignores the award?
Failing to comply with an award is a criminal offence under the Act, with a fine of up to RM250,000, imprisonment of up to three years, or both, plus up to RM5,000 for each day the offence continues. The winning party can also register the award with the court and use normal enforcement routes such as garnishee proceedings or a judgment debtor summons. An award made in a party’s absence can be challenged with Form 16 within 30 days, and a party can seek judicial review in the High Court within three months on narrow grounds.
Where is the tribunal for Johor owners?
The TPPS has its headquarters in Putrajaya and zone offices, with the Zon Selatan (southern zone) office in Johor Bahru, at Ibrahim International Business District. Hearings are also held in Muar. For a JB owner, that means a dispute can usually be handled locally.
Common situations and what you can ask for
| Situation | Usually filed by | What you can seek |
|---|---|---|
| An owner has not paid maintenance and sinking fund for months | JMB or MC | An order to pay the arrears with interest |
| A leak from the unit above is not being fixed | The affected owner | An order to repair or pay repair costs |
| A meeting or resolution did not follow the rules | An owner | An order invalidating the proceedings or nullifying the resolution |
| A request to see accounts or documents is refused | An owner | An order to disclose the information |
Knowing this route exists often helps settle matters before a claim is ever filed.
Tips before you file
- Try the AGM or the committee first. Many issues resolve once raised formally.
- Keep records: billing statements, photos of leaks, inspection reports, emails and minutes.
- Check the by-laws for any rule that already covers your issue.
- Be specific about what order or amount you want.
The tribunal is one of the strengths of Malaysia’s strata system: owners in buildings like Causewayz Square have a fast, inexpensive route if a dispute ever arises. To understand the bodies involved, read our guides to the JMB and MC and the sinking fund, or our JB maintenance fee guide. WhatsApp us for the latest SPA price list and floor plans.
Sources
- KPKT: Tribunal Pengurusan Strata (client charter and offices)
- KPKT: TPS forms list
- EdgeProp (Nov 2022): 80% of strata tribunal claims are fee related
- Mondaq: 10 things to know about the Strata Management Tribunal
- Berita RTM (July 2025): KPKT resolves 6,505 TPPS cases
- Berita RTM (Oct 2025): e-TPS digital claim filing
This guide is general information, not financial advice.